align
B

stage 1 — concept design

hill house, deviot

client: naomi reid · designer: saxon hall · 3,200 deviot road

estimate due 22 may
  1. sales
    lead → commencement
  2. sketch
    stage 0
  3. 3concept
    stage 1
  4. 4DA
    stage 2a
  5. 5interior
    stage 2b
  6. 6CD + BA
    stage 3

updates

weekly notes from align — what's moved, what's coming, what we need from you.

  • S

    saxon hall

    principal architect · week of 13 may

    estimaterfi

    concept estimate package is in your portal — full pack with specs, glazier inclusions (viridian flushglaze) and interior budget assumptions. estimate due back 22 may. two RFIs still open: cladding spec on section A2, and the suspended slab edge on the north elevation. we're meeting tuesday 21 may at 2pm to walk through the estimate together.

  • S

    saxon hall

    principal architect · week of 6 may

    sign-off

    naomi signed off the final sketch. ECI is in place. we've moved straight into concept and the structural approach is being detailed with the engineer this week. i'll send the prelim engineer review for your input by friday.

  • S

    saxon hall

    principal architect · week of 29 april

    site

    good site walk with you and naomi. confirmed access via the eastern boundary, services run along the road frontage. we agreed the platform position pending council overland flow check — i'll flag if that shifts.

joint meetings

  • concept presentation — client + designer

    this week

    thursday 16 may · 9:30 am

    n
    s
    y
  • builder estimate review

    next week

    tuesday 21 may · 2:00 pm

    s
    y
  • estimate sign-off with client

    soon

    thursday 30 may · 10:00 am

    n
    s
    y

estimate package

concept estimate — issued 12 may

full package with specs, glazier inclusions, and interior budget assumptions.

due

22 may

open RFIs

2

docs

14

open RFIs & buildability notes

  • confirm cladding spec — section A2

    you · 2 days ago

    RFI
  • suspended slab edge detail to north elevation

    you · 4 days ago

    RFI
  • recommend simplifying the entry portal — buildability + cost

    you · 6 days ago

    note
  • ridge height — saxon confirmed 6.8m

    closed by saxon · 8 days ago

    resolved

shared with you

  • concept design pack v1

    updated 12 may · saxon hall

  • concept estimate package

    issued 12 may · saxon hall

  • needs & wants — hill house

    signed · stage 0

  • sketch design — final option B

    signed · stage 0

ask align

what changed in the concept since the sketch sign-off?

instant answers from saxon's notes, drawings, and the estimate package — sources cited.